Commissioning engineers run two independent checks on a new pedestrian footbridge…
PHYSICS · Multi-part · Fermi University Physics · Mathematical Methods for Physics · Thermal, Statistical & Complex Systems · Temperature, heat and the macroscopic behaviour of matter
Conditions of Validity, Ch Green functions: inverting the operator
Problem
Commissioning engineers run two independent checks on a new pedestrian footbridge before it opens. Check 1: load-deflection reciprocity. The deck cable, of length L=12.0m, is modelled as a light, perfectly flexible cable under uniform tension T=4.0×105N, pinned at both supports (u(0)=u(L)=0). Self-weight sag is ignored, and only the incremental transverse response to a small point load is modelled, so a load F at x=ξ produces a deflection u(x) satisfying −Tu′′(x)=Fδ(x−ξ). Check 2: thermal pulse test. A suspect weld in the steel anchor block is tested by depositing Q=500J of resistive heat instantaneously at the weld, treated as a point source in an effectively infinite homogeneous solid with ρc=3.5×106Jm−3K−1 and thermal diffusivity D=1.1×10−5m2s−1.
((a)) A test actuator applies F=750N at x=3.0m. Using the closed-form Green function for the tensioned cable, find the deflection at the sensor at x=9.0m.
((b)) Without repeating the boundary-value calculation, state the deflection that would be measured at x=3.0m if the same 750N load instead acted at x=9.0m, then verify it directly from the closed form. Name, in one sentence, the property of the operator that guarantees the two readings agree.
((c)) An embedded sensor sits r=25mm from the weld. Find the temperature rise it registers t=2.0s after the pulse.
((d)) Find the time at which the sensor's reading peaks, and the value of that peak.